Rebuilding the Pentagon
Project Phoenix: A Stronger Pentagon Rises from the Ashes

On September 11, 2001, the first of five Pentagon building sections or "wedges" to be renovated under a 14-year plan was five days away from completion. That morning, a Boeing 757, hijacked by terrorists, went through a corner of that wedge before ending up in a second, un-renovated building wedge. More than 2,600 workers were in the disaster area, but there were only 125 casualties, thanks in large part to just-completed structural renovations. In all, a million-square-foot area was damaged and about 400,000 square feet of space had to be demolished after the 9-11 attack.
Now, almost ten months later, like the fabled phoenix bird that rose from the ashes of its destruction, the Pentagon is rising stronger and safer from the destruction of 9-11. Contractors working on Project Phoenix, as the rebuild of the terrorist-damaged section was named, are working at an extraordinary pace to meet a September 11, 2002 deadline to have the damaged wedge of the outer "E" ring of offices rebuilt and ready for occupancy.
A New, Stronger Roof
Part of the Pentagon's new strength comes from its new roof system. More than 250 pre-engineered Alpine TrusSteel CFS trusses, manufactured by Panel Systems, Inc. (Lorton, VA) support 25,000 SF of interlocking Steel Edge Creteplank concrete deck units supplied by Martin Fireproofing, Inc. (Buffalo, NY). As of late June of this year, Facchina Construction Company (LaPlata, MD) has completed the installation of the trusses and deck units. The trusses and decking, as well as the slate roofing, provide a strong, tough, fire-resistant roof system - just what the project design team, led by Allyn Kilsheimer (KCE Engineers, Washington, DC) and Keith Davis (Law Engineers) were seeking.
Perhaps the biggest challenge facing all those working on Project Phoenix is the fast pace of construction. According to Nick McIntosh, Assistant Project Manager for Facchina, "I would call Phoenix a super fast track project." Facchina is the contractor on Phoenix responsible for the concrete work and the roof system. "From the beginning, we needed to pick our vendors and subs very carefully. Facchina interviewed several truss vendors, but Barry Unger of Panel Systems made a significant commitment to service and bought into the fast track project requirements. Throughout the project, they made good their commitments. Panel Systems and Alpine met with us several times on the roof to examine existing conditions and take field measurements. Their careful engineering efforts paid off - the trusses fit like a glove, with no fieldwork necessary. Working with Panel Systems was a breeze."
A Strong Team
In order to deliver this roof system on time, Barry Unger, president of truss manufacturer Panel Systems, Inc. worked with a team composed of his manufacturing staff as well as truss designers Atlantic Framing Design (Cockeysville, MD), truss technology provider Alpine Engineered Products, Inc. (Pompano Beach, FL), and roof panel manufacturer Martin Fireproofing (Buffalo, NY). Additional engineering was provided by Alpine's TrusSteel partner, Unimast, Inc. (Schiller Park, IL).
Brian Mucha, P.E. (Atlantic Framing Design) provided truss system designs for the project. "We were honored to work on this project, not only because it was the rebuild of the Pentagon, but also because Panel Systems and Facchina would consider us to be a part of their team", said Mucha. "When we discovered the complexity of the project, we knew that we would have to lean on Alpine for some in-depth engineering analysis and design. Several elements of the roof design made this project even more interesting. First, an advanced fall protection system (from Hy-Safe Technology, Union Grove, WI) required that man-harness stanchions be attached to the top of many of the trusses. The trusses had to be designed to take the impact load of a falling worker, caught by the harness. This safety system also necessitated an innovative connection to anchor the stanchions to the trusses. Second, some fairly complex calculations were required to account for the differences in thermal expansion between the Alpine trusses and the supporting concrete. Alpine and Unimast engineers working together came through with all the required calculations in a timely manner and helped us all stay on the project timeline. Our engineers designed an unusual slotted base connection for the trusses to make it all work."

A Strong Deck
"Working with the Martin Fireproofing concrete plank roofing system was a cakewalk", commented Facchina's McIntosh. "It really is a beautiful material, the way it interlocks so easily. You can't beat concrete panels for fire safety." Atlantic Framing Design's Mucha added, "With the Martin Fireproofing roof deck system, and the stability of the TrusSteel trusses, the truss permanent bracing required on the project was really minimal."
A Strong Commitment
Barry Unger recalls his feelings the day he found out that his company had won the bid to provide cold-formed steel roof trusses on the rebuild of the Pentagon. "I felt honored to be selected to work on the Phoenix project, to work along with such an all-star team. I also knew that we were going to have to really work hard and smart to meet the tight time schedule and the demands of the design." Unger said recently, " I am very excited to be involved in the project, working with the highest level of people on this historic renovation. I know all of our employees are also very proud to be a part of this project, especially since it is right in our back yard. I believe any one of us would do anything to help restore the Pentagon. As you can imagine, this project has been the number one priority at Panel Systems since it began. At times, some of our other jobs had to be put on the back burner because of the urgency of Project Phoenix, but all of our customers have expressed their agreement and understanding of our priorities."
A Strong Finish
Nick McIntosh has similar feelings about working on Project Phoenix. "There will be pressures on any super fast track job. But, I would not trade the privilege of working on this project for any other project, regardless. At Facchina we feel that working here is an honor, and it is a privilege to be able to make a contribution. At times, we had to put our family lives on hold - many families made sacrifices just as did the workers. Let's just say we worked a few weekends." Nick is modest. At the project topping out ceremony, he received a trophy from the Deputy Secretary of Defense for his work on site logistics and maintaining the tight project schedule.
"Since 9-11, virtually every American has wished that he or she could have a part in the healing and rebuilding ", says Panel System's Barry Unger. Project Phoenix has been a challenge for us, and a way for Panel Systems to play a part in this great effort. As a company, we will never forget the "Let's Roll" motto for the project and how it inspired all of us to work harder than usual to get the job done." Facchina's McIntosh agrees, "Everyone on this project is proud of our work here. We all share a common interest - to erase the ugliness created by the terrorist attack".
Project Phoenix, the rebuilding of the Pentagon, was completed on-schedule. The destroyed section of the Pentagon was reopened, with a national ceremony, one year after the terrorist attack.
This article was published in the Sept. / Oct. 2002 issue of Structural Building Components magazine.
Location : Arlington, VA
Project Completion : 2002
Architect : RTKL (Washington DC)
Engineer : KCE Structural Engrs. (Washington DC)
General Contractor : AMEC plc
TrusSteel Fabricator : Panel Systems, Inc. (Lorton, VA)
Truss And Roofing Installer : Facchina Construction Co. (La Plata, MD)
Special Engineering : Alpine Structural Consultants
Project Description : Military
Davis-Monthan AFB
TrusSteel Flies High at Davis-Monthan Air Force Base
A flight of TrusSteel CFS trusses took to the air above Davis-Monthan Air Force Base (Tucson, AZ) recently. Seven entire sections of the new roof - complete with trusses, bracing, roofing, mechanical systems - landed atop the new dormitory buildings without a hitch (no touch-and-gos needed). "It has gone very smoothly", commented Glenn Lee, Project Superintendent, Sundt Companies Inc.
When asked for reasons for assembling the large sections on the ground and then lifting them to the top plate (a technique called rafting), Kevin G. Almquist, Project Manager, Sundt Companies Inc. replied, "Safety, time, productivity - all those are reasons." When asked about how much time was saved using TrusSteel and rafting, Kevin replied, "Overall, as a conservative estimate for the project, we feel that we have saved two to four weeks". Glenn Lee had his own reasons for liking the rafted installation approach. Glen said, "Safety is a big thing. And, we installed ductwork, sprinklers, chilled water and domestic water piping on the ground. That alone was a big time saver, as opposed to working off ladders and trying to feed all that through the trusses."
Kevin Almquist summed it all up with his comment: "Overall, we are just thinking out of the box."
More "Out of the Box" Thinking
Alpine Structural Consultants provided engineering assistance for this project. According to Sowri Rajan of Alpine Structural Consultants (ASC), "Kent Bice in the TrusSteel engineering department in Haines City designed the truss bracing for the 50' x 56' sections of the roof system as well as for the big 70' x 70' section. He also designed the locations of the pick points of the raft assemblies as well as the pick lift mechanism and its attachment to the beam supporting the trusses. A HSS 6x2x3/8 tube steel beam (that's a 2" deep x 6" wide x 3/8" thick Hollow Structural Steel section) at both ends of each assembly supported the TrusSteel trusses."
The installation plan, as devised by the installer JB Steel and ASC, was to fabricate the roof section on the ground with the trusses supported by the HSS beams, and lift the section to the top of CMU walls. Kent's design work included the designs for the temporary bracing of the truss bottom chord and the permanent bracing for truss webs. The trusses were spaced at 2' O.C., with approximately 26 roof trusses in each rafted assembly. The roof trusses supported mechanical equipment, which was installed by the mechanical contractor prior to each lift.
A Famous Site
You can visit the Davis-Monthan AFB on the Web at http://www.dm.af.mil/. Davis-Monthan is the current home of the 355th Wing, one of the largest wings in the Air Force. It is also the home of the famous 12th Air Force, which was started by Jimmy Doolittle in 1942, distinguished itself in Africa during WWII, and continues to serve in recent operations such as DESERT SHIELD and DESERT STORM.
Location : Tucson, AZ
Project Completion : 2003
Architect : Madsen, Flathmann, Dameron & Babcock Architects
Engineer : Caruso Turley Scott Structural Consultants, FL
General Contractor : Sundt Companies Inc, Tucson, AZ
TrusSteel Fabricator : Gecko Steel Truss LLC, Yuma, AZ
Truss And Roofing Installer : J. B. Steel LLC, Tucson, AZ
Special Engineering : Alpine Structural Consultants
Project Description : Multiple dormitory buildings
Fort Wainwright
TrusSteel Flies in Alaska

TrusSteel CFS trusses provide structure for sloping roofs on the new Lodging Facilities buildings at Fort Wainwright in Fairbanks, Alaska.
According to the Army, the Fort Wainwright complex is "the home of the Arctic Warriors", but no one wanted a battle when it came to building the roofs on the new Lodging Facilities. When you build in Alaska, a lot needs to happen quickly or you will find yourself standing in snow. By "rafting" or building entire roof sections of trusses on the ground and lifting the completed sections into place, the contractor not only saved time but provided a safer working environment.
Done Right - On Time
These trusses had to be done right and right on time. This challenging project tapped into fabrication savvy of Titan Manufacturing, the services of the TrusSteel Design Team as well as the engineering services of Alpine Structural Consultants. TrusSteel Design Team leader Donny Kirkland provided truss layout and preliminary components design as well as material lists. The ASC Engineering Team, led by Sowri Rajan, provided full roof system design (red iron framing excluded) which included:
Permanent bracing design by BBD's Kent Bice, PE,
Roof deck, truss-to-bearing connections, and lift bracing design, and coordination by TrusSteel’s Sowri Rajan, PE, with
All drawings reviewed, signed and sealed by Trussteel’s Bob Keim, PE.
By applying tight teamwork and aggressive scheduling, both engineering and finished trusses arrive on time. This contractor was NOT left out in the cold.
Fort Wainwright
Location : Fairbanks, AK
Project Completion : 2004
Architect : Corps of Engineers
Engineer : Design Alaska, Inc. , Fairbanks, AK
General Contractor : GHEMM Co., Fairbanks, AK
TrusSteel Fabricator : Titan Manufacturing, Anchorage, AK
Truss And Roofing Installer : GHEMM Co.
Special Engineering : Alpine Structural Consultants
Project Description : Lodgings
